Working in Resource View
Resources are the lifeblood of any project, without which an idea will never reach fruition. Effective management of personnel, equipment, and raw materials is key to bringing your project to a successful conclusion, and OmniPlan provides the tools you need to do just that.
In OmniPlan, resource management is primarily accomplished in Resource View (the second button in the toolbar’s view switcher). This chapter describes the functions and features of the view; the Task and Resource inspectors also contribute to resource organization.
Resource Types
An understanding of the various resource types available in OminPlan is useful when beginning work in Resource View.
Staff
The most important resources on a project are likely the people responsible for its execution. These are represented by Staff resources in OmniPlan. As unique humans, each staff member is represented by an email address that identifies them across all projects they may be a part of.
Equipment
Tools, machinery, computers, and other hardware used to complete a project are represented as Equipment resources in OmniPlan. Equipment are similar to staff in many respects, but lack a notion of unique identity.
Material
Ingredients, building supplies, food, or other components expended in the process of executing the project are represented as Material resources in OmniPlan. Unlike staff and equipment resources, materials dedicated to tasks are consumed upon use and are therefore represented by a number of units required.
Group
A Group isn’t a resource itself. Instead, it’s a way to gather other resources under the same umbrella, indicating that (for example) a number of staff are part of the same team. When a group is assigned to a task, the task’s effort is split evenly between all of the resources in the group.
Creating and Deleting Resources
A key part of building out your project is describing the resources that make up the team you’re working with, and the equipment and materials they’ll be using to get the job done. The resource outline is a quick and efficient way to do this.
There are several ways to create new items in Resource View:
- Select an item in the resource outline and press Return (or Command-Return, depending on the Keyboard Options in OmniPlan’s General Preferences).
- Click the Add button in the toolbar above the outline.
- Drag a Contacts card into the resource outline to create a Staff resource that collects its contact information from the Contacts.
- Secondary-click and choose Add ▸ Resource from the contextual menu.
There are a few ways to delete a resource or resource group:
- Select a resource or group in the outline, then press the Delete key.
- Select the item, then click the Remove button in the toolbar above the outline.
- Select the item, then Control-click to reveal the contextual menu and choose Delete.
Assigning Resources to Tasks
Most tasks require some kind of resources in order to complete. Software development needs programmers, excavation needs heavy machinery, and construction needs lumber. Tracking which resources are assigned to which tasks helps you to see how long the tasks will take to complete, and when your resources are going to be busy or idle.
There are several ways to assign a resource to a task:
- Select the task in task view, open the Assignments section of the Task inspector, and check the resources you’d like to assign. You can then edit the amount to assign, if it’s different from the default amount. You can also see all of a resource’s assignments, and adjust their amounts or clear them, in the Assignments section of the Resource inspector.
-
Drag tasks around between resources’ lanes and the Unassigned lane in the resource timeline chart. While dragging a task from one resource to another, you can hold the Option key to assign the task to the second resource without unassigning it from the first.
-
Drag a card from Apple Contacts to a task in the task view. If the project doesn’t yet have a resource associated with that card, a new one is added.
-
Edit the Assigned column of the task outline or the assigned resources area in the Gantt chart. The following are helpful hints:
- Enter resource names in the Assigned column to assign them to the task.
- You can also double-click resource lists in the Gantt chart and edit them directly there.
- Follow a staff resource with a percentage inside curly braces to assign an amount other than 100%.
- Follow a material or equipment resource name with a number in curly braces to assign an amount other than 1 unit.
- Separate multiple resource names with semicolons.
Assigning Groups
If you assign a resource to a group of tasks, the resource is assigned to every task in the group. The group itself cannot have a resource assigned to it.
If you assign a group of resources to a task, OmniPlan provisionally labels the task as having the whole resource assigned. Then, when you level resources, one member of the group is chosen to work on that task. If that member becomes unavailable, leveling again assigns a different member.
Characteristics of Resource Groups
A resource group is just a way to organize several resources together, so it doesn’t have a lot of the same characteristics as an individual resource, like Efficiency and Cost.
-
Name—Of course, a resource group has its own name.
-
Email—You can assign an e-mail address to a group, in case you have a mailing list or some address which goes to all of the members in the group.
-
Type—A resource group can contain resources of any type (Staff, Equipment, or Material), but its own type is always Group.
-
Cost/Use, Cost/Hour, and Efficiency—These are shown as averages of the values of all members of the group. If you enter a new value, it is applied to all members of the group.
Tracking Assignments with the Timeline
When you want to manage your project from the point of view of the resources available, the timeline in Resource View will help you visualize and control your assets.
-
Click the bar graph button to show or hide the resource allocation graph beneath each resource’s timeline.
-
The chart shows a timeline of tasks for each resource you select in the outline. If you select no resources, the chart shows all resources’ timelines. If the resource is unavailable during some normal working hours, because it has customized working hours, the unavailable times have a background of the Off-hours color (gray by default) as it is set in Styles View.
-
Below the resources’ timelines, an Unassigned timeline shows the tasks which aren’t assigned to any resource. You can drag tasks between timelines to change their assignments.
-
A blue bar in the load graph represents time when the resource is being used at 100% of its available units.
-
A pink bar in the load graph represents time when the resource is being used at over 100% of its available units. You can level the project to clear up such problems.
-
You can zoom the timeline the same way you zoom the Gantt chart. Just choose a scale from this menu or drag in the header area.
Setting Resource Attributes
Use the Resource Inspector (or the corresponding columns in the resource outline) to set the properties of a resource such as its Type, Units, Efficiency, and Cost. It can be important to understand the use for each of these attributes; some additional detail is provided here.
- Units vs Efficiency
-
The amount of a staff member’s time dedicated to the project (relative to their full time schedule) is expressed by the resource’s Units value in the Resources inspector (or column in the resource outline). If Ivan’s time is split between two projects that he spends equal time on, his Units value for one project should be set to 50%, and 100% of his effort value applied to a task in this project equates to 50% of his total time on the clock.
A new trainee’s work might not be as productive as that of an experienced employee. In that case, the resource representing them should have its Efficiency value reduced while they are in training. This represents the amount of effort-per-time the team member contributes to tasks to which they are assigned; 100% of their effort accomplishes less than 100% of the effort of a fully trained worker.
As an illustration of the difference between Units and Efficiency, consider a resource that costs $100 per hour and is assigned to a task at 50% Units. An hour of effort applied to the task will cost $50.
If a similar resource is assigned at 100% units but has 50% efficiency, an hour of effort (an identical amount of work done) costs $100.
- Cost per Use vs Cost per Hour
-
A resource that has a static cost each time it is employed for a task—regardless of the effort or duration required—has its cost represented by a Cost per Use value, where assignment to a task represents one use. This may be a flat rental fee for equipment (for example), or it might reflect the nature of the task to which the resource is assigned. An illustrator contracted to produce a book cover, for example, may charge a flat fee for the job regardless of the number of hours worked to reach the end result.
A resource with cost that scales based on the duration of its employment, by contrast, is represented by Cost per Hour. This could reflect costs of running a physical plant (heating, electric, other utilities), or the wages of a salaried or hourly employee.
The Working in Calendar View chapter explains how to set up a resource’s working hours and schedule exceptions.
View Options in Resource View
As with Task View, the resource outline can be customized to display columns with a wide variety of information about your resources. To show and hide columns, select them in View Options (Command-J) or Control-click on the column header and toggle them in the contextual menu that appears.
Also as with Task View, the Resource View’s view options offer metadata fields for display next to (or superimposed upon) tasks and groups as displayed in the resource timeline. Each appended field has a dropdown menu that you can choose any of the available custom columns’ values to occupy.
Description of some of the more involved custom Resource View columns follows.
- Attachments
- You can click the paper clip icon Attachment icon in the selected row to see a menu of the item’s attachments, or to link to a file if there isn’t one linked yet. Rows with links to files show a paper clip icon even when they are deselected.
- Notes
- You can click the note icon in the selected row to show or hide the item’s note, or to create a note if there isn’t one yet. Rows with notes show a note icon even when they are deselected.
- Unique ID
- The unique ID is a number assigned to each resource to identify it unambiguously, even if its name or position in the outline changes. A unique ID won’t ever change, and each new task or resource you create gets a new unique ID number. These numbers are useful for matching up items when you are importing and exporting projects between OmniPlan and other applications.
- Custom Work Week
- An icon appears in this column if a resource has a work week that differs from its default work week; the default work week for a resource is defined by its parent (if it’s a member of a group) or the project (if it’s not). You can click the icon to see the resource’s work week, and from there you can always click the X button in the upper-right of the week view to revert to the default.
- Schedule Exception
- An icon appears in this column if a resource has a work schedule that differs from its work week, such as when someone goes on vacation. You can click the icon to see the resource’s work schedule, and from there you can check the orange-highlighted dates to see where its exceptions are. You can click the X button in the upper-right corner of any week view to clear the resource’s exceptions for that week.